12/2010 Commissioning of the first solar thermal plant in Egypt begins
12/2010 Start of preparation works for construction of the fourth-Spanish plant Ibersol and the Blythe facility
10/2010
Final construction permit for the Blythe power plants in California, the largest solar energy facility in the world
05/2010
Merger of technology and power plant construction subsidiaries Flagsol and MAN Solar Millennium completed
03/2010      Establishing the Solar Millennium Invest AG for the distribution of green investment products
10/2009 Joint venture DII established and ready to take up work to implement the Desertec concept
07/2009 Solar Millennium successfully completes sale of stakes in Andasol 1 and 2
07/2009 Andasol 1 is officially inaugurated
07/2009 Solar Millennium has become a founding member in Desertec Industrial Initiative for solar power production in the MENA region
07/2009 Stadtwerke München, RWE Innogy, RheinEnergie and Ferrostaal enter Andasol 3
05/2008 Solar Millennium wins Energy Globe Award for initialising and developing the first parabolic trough power plant in Europe
04/2008 Start of the R&D project Blue Tower
03/2008  Increase of share capital to 12,500.0 thousand EUR
11/2007  
Technology subsidiary Flagsol is commissioned with the first parabolic trough field in Egypt (Kuraymat)
05/2007
Joint venture with MAN Ferrostaal for power plant construction
12/2006 Financial Closure for Andasol 2 (start of construction 02/2007)
05/2006 Financial Closure for Andasol 1 (start of construction 06/2006)
02/2005 Increase of share capital to 9,915.5 thousand EUR (through several capital increases from 2002 to 2004)
09/2003 Cooperation with the ACS/Cobra Group and later entry in Andasol 1 and 2 with 75%
06/1999 Creation of the Solar Millennium AG corporation by changing the legal status
10/1998 Founding of Solar Century Management GmbH (from 03/1999 Solar Millennium GmbH)